OpenAI weighs leasing Ohio data center with Nvidia backing, The Information reports

Avatar

Published

on

By Reuters | Updated: June 10, 2026

June 9 (Reuters) – OpenAI is in talks to lease a proposed 10-gigawatt data center campus ​on federal land in Ohio, in a deal ‌that could include financial backing from Nvidia (NVDA.O), The Information reported on Tuesday, citing two people with direct knowledge of ​the discussions.

Here are some details:

  • The campus could cost ​at least $500 billion to build, based on current prices ⁠for chips, labour, power and other inputs, the ​report said.
  • OpenAI would control the equipment at the facility ​under a 20-year lease, with payments starting once operations begin; the first phase is expected in 2028, the report added.
  • The facility, among the ​largest of its kind, would be developed by ​SB Energy, a unit of SoftBank (9984.T), opens new tab, on Department of Energy land ‌in ⁠southern Ohio.
  • Nvidia is expected to supply hardware in the facility and provide a financial guarantee for OpenAI’s lease and SB Energy’s financing, according to the report.
  • Reuters ​could not immediately ​verify the ⁠report. OpenAI and Nvidia did not immediately respond to Reuters’ requests for comment ​outside regular business hours.
  • Earlier this year, the ​ChatGPT maker paused ⁠its proposed ‘Stargate’ data centre project in the UK, citing regulatory hurdles and high energy costs.
  • Separately, Apollo (APO.N), opens new tab and Blackstone (BX.N), opens new tab ⁠are financing ​a $35 billion AI capacity expansion ​for Anthropic using Broadcom (AVGO.O), opens new tab chips, Reuters reported this week.

Reporting by Bipasha Dey ​in Bengaluru; Editing by Sherry Jacob-Phillips and Eileen Soreng